The curb ramps at SE 77th are finished. The crossing island is still ahead.
Portland Bureau of Transportation
PBOT’s November 17 update confirms the new accessible curb ramps at SE 77th Avenue and Division Street are complete. Crews expect to return in December to finish the concrete refuge on the west side of the intersection. At SE 64th Avenue, the other crossing in the project, PBOT reports substantial completion in August. Portland’s voter-approved gas tax funds both, with budgets of $400,000 at 77th and $234,000 at 64th. The bureau has not published final payments on the project page.
Editorial illustration
Why it matters here
The ramps give people using wheelchairs or strollers a way onto the west crossing at 77th. The planned island would let them cross one direction of traffic at a time.
Two Division Street crossings reach different stages
At SE 64th Avenue the crossing was substantially complete, with lighting and pavement repairs outstanding. At SE 77th Avenue crews were finishing accessible ramps ahead of paving and a median island. Portland’s voter-approved gas tax funds the two budgets: $234,000 at 64th and $400,000 at 77th.
Two separately listed crossing budgets
SE 64th and Division$234,000
SE 77th and Division$400,000
Budgets displayed on PBOT’s crossing-project page. The intersections have different work and funding sources; these are not equal-scope unit costs or final construction payments. Source
Why it matters here
Someone crossing Division at 77th still had to wait for the median refuge, while the crossing at 64th was already substantially complete.
What you can do
Find your intersection on the project page and check the separate status, design and budget entries for 64th and 77th. Portland project update and budgets
Jade–Montavilla is substantially complete. Published cost figures need context
Portland Bureau of Transportation
As checked November 20, PBOT labels the Jade and Montavilla multimodal project substantially complete. The City’s project list places it in districts 1 and 3. The project webpage gives a $9.094 million funding package, while the 2025 Fixing Our Streets annual report lists an $11,230,691 total project budget for Jade–Montavilla Connected Centers. The records reviewed do not explain whether timing, scope or accounting boundaries cause that difference. Neither number is a final paid-cost statement, so the difference alone does not establish an overrun.
Editorial illustrationThe funding mix listed on the project page
Federal funds$3,200,000
ARPA funds$4,900,000
Development charges$994,000
The webpage lists a $9.094 million funding package. These are funding sources, not final payments. The separate annual report uses a different project-budget total, so the two totals need reconciliation before drawing a cost-overrun conclusion. Source
Why it matters here
Residents can see which improvements reached their streets. The two published budget figures leave open how much the city ultimately paid for that work.
What you can do
Open page 39 of the annual report to see which costs its $11.23 million entry covers, then compare it with PBOT’s $9.094 million funding figure. 2025 annual report, page39: budget and districts
Question we’re following How do the $9.094 million funding summary, $11.231 million budget and final project costs reconcile?
Gateway street project heads to a second Council reading
Portland City Council
Portland City Council advanced an ordinance that would let the transportation bureau acquire property rights along Stark and Washington. Council scheduled the second reading for December 2 at 9:30 a.m. The $11.7 million estimate covers design and construction along the corridor. The ordinance does not set prices for individual easements.
Editorial illustration
Why it matters here
Getting the corridor ready for construction could require temporary access or permanent rights on individual properties. Compensation for each acquisition remains open.
What you can do
Open Exhibits 1–72 on the ordinance page to see the property interests under consideration before the scheduled Dec. 2 second reading. Ordinance and Council action
Question we’re following What easements will be needed, and what will the City ultimately pay?
Portland’s $11.7 million funds the whole Gateway corridor. A 2019 worksheet put beacons, lighting and signal connections at four crossings at $800,000. What would those four crossings cost under today’s design?