Why do two public records differ by $92,580?
Add the five amounts on PBOT’s project page and the total is $11,800,629. The presentation attached to the November 18 Council item shows $11,708,049 for the corridor. Both describe funding. Actual payments to engineers, contractors or property owners would appear in expenditure records.
The largest change is in regional flexible funds. Metro’s 2022 committee papers describe moving about $120,000 from the corridor project into a separate project for travel outreach, combined with similar work on another route. That matches the reduction in the regional line. A July 2025 Metro programming report also shows $5,212,000 in federal funds.
The Council slide separately lists $26,801 in development charges and $619 more in general transportation revenues. The project page divides its general revenues between ADA ramps ($511,629) and quick-build work ($200,000). Read from the project page to the Council slide, the changes add up to −$120,000 + $26,801 + $619 = −$92,580.
Funding sources for the corridor. Project page checked November 20, 2026. Council presentation attached November 18, 2026.
| Funding source | PBOT project page | Council slide 5 |
| Regional flexible funds | $5,332,000 | $5,212,000 |
| Fixing Our Streets | $5,030,000 | $5,030,000 |
| Clean Energy Community Benefits Fund | $727,000 | $727,000 |
| General transportation revenues | $711,629 | $712,248 |
| Transportation system development charges | No separate line | $26,801 |
| Total of listed amounts | $11,800,629 | $11,708,049 |
What else matters
Metro’s July 2025 phase budget totaled $11.442 million. It allocated $8.542 million for construction, $2 million for preliminary engineering, $800,000 for property rights and $100,000 for utilities. Compensation for the current acquisitions remains subject to negotiations.
A question worth asking
When were the two local lines revised, and which funding schedule is current for each phase? A dated project ledger with transfers and expenditures would let residents trace those changes and see what has actually been spent.
PBOT project page and funding listFunding table in the Council presentation, slide 5Metro committee packet, March 4 minutes and staff summary for key 22138 (search “$120,000”)Metro programming report, July 31, 2025, project 71091, p. 113