A Tryon Media Group publication
Our publications
Portland, In View
Streets & neighborhoods

Why spend $11.7 million on Gateway’s Stark and Washington streets?

What would it cost to make four crossings safer? Two city records price different things, seven years apart. Neither gives a current price for the crossings alone.

What changed
Portland’s $11.7 million project covers a corridor. An earlier $800,000 estimate covered equipment at four crossings.
Why it matters here
People walking, rolling or driving along Stark and Washington will see different changes by intersection. The crash records show where injuries were reported.
What you can do
Check the Council docket for the property-rights decision and current participation instructions. Compare the crossing nearest you with the others below. Council docket and testimony
Send a correction

What the two figures cover

November 18, 2026$11,708,049

Funding for the whole corridor

Five funding sources support the larger Stark and Washington project, from design and property rights to construction.

Council presentation, slide 5
June 2019$800,000

One installation line for four crossings

Engineers priced pedestrian hybrid beacons, supplemental lighting and signal connections at 100th and 105th on Stark and Washington. The line covered all four crossings together.

Engineers’ worksheet, page 6, item 17

The open question What will the four crossings cost in the current design? The next itemized engineer’s estimate or awarded bid could answer it.

Compare the crash record · Read the cost breakdown
Scheduled

Portland City Council

Property rights for the Gateway street project

Council scheduled a second reading on whether PBOT can acquire temporary and permanent property rights to build the project. The ordinance concerns acquisition authority. The $11.7 million figure covers the entire corridor design and construction project.

Will Council authorize PBOT to acquire the easements it needs for construction?

Illustration of a pedestrian and a cyclist across a rain-darkened crosswalk, with a crossing button and textured curb ramp in the foreground.
01The safety case

What happened at Washington and 105th?

Portland’s transportation bureau records one pedestrian crash at Washington and 105th in its review of the corridor. Its intersection notes give no date or injury severity for that person. PBOT describes a wider problem behind the project: busy one-way streets, long crossings and a history of people being struck. Across the project area, the bureau counted 50 Vision Zero crashes and three deaths from 2015 through 2022.

At 105th, PBOT observed 40% of drivers on Washington and 60% on Stark exceeding the posted 30 mph limit. East of the freeway, a person crossing Washington faces 48 feet of pavement and four travel lanes. The draft design pairs a refuge island with an improved bus stop at 105th. Someone getting off a bus would have a place to pause partway across.

PBOT existing conditions report, crash map and intersection notes, pp. 10–11
PBOT open house, crossing distances, speeds and traffic volumes
May 2026 draft design, block by block
02Compare intersections

Where did crashes concentrate?

Three blocks west of 105th, Washington and 102nd had the highest count on PBOT’s map. The figures below follow Washington from 99th through 107th, using the intersections identified in the report’s notes. The 102nd Avenue crossings also feature in the planned signal upgrades.

PBOT’s Vision Zero count includes every reported pedestrian or bicycle crash and any crash involving serious injury or death, regardless of how the person traveled. A count of one pedestrian crash alone does not establish the person’s injury severity.

2015–2022 · All travel modes

Crashes along SE Washington

One filled dot represents one recorded Vision Zero crash.
  1. 99th Avenue 5
  2. 100th Avenue 5
  3. 102nd Avenue 8
  4. 103rd Drive 2
  5. 105th Avenue 1
  6. 106th Avenue 0
  7. 107th Avenue 0

The counts do not account for how many people use each crossing.

View the data table
Same corridor and reporting period, 2015–2022. All travel modes. Zero denotes an explicit zero in PBOT’s notes.
SE Washington atRecorded Vision Zero crashes
99th Avenue5
100th Avenue5
102nd Avenue8
103rd Drive2
105th Avenue1
106th Avenue0
107th Avenue0

What else matters

More people may cross at one intersection than another. These counts cannot establish risk per crossing or a citywide priority ranking. The map supplies the period totals. The notes also mention a 2023 death at 102nd, which we exclude from this comparison.

A question worth asking

What did pedestrian demand, distance to the next usable crossing and vehicle speeds contribute to the decision at 105th? A comparison of the candidate sites and designs would let residents see how PBOT weighed those factors.

PBOT existing conditions report, crash map and intersection notes, pp. 10–11
PBOT open house, crossing distances, speeds and traffic volumes
Project design and community survey results
PBOT’s definition of a Vision Zero crash
03Across Portland

Does this stretch appear on Portland’s high-crash list?

In a separate citywide comparison for 2020–2024, Washington and 102nd ranked 18th on PBOT’s list of 20 high-crash intersections for pedestrians. Three pedestrian crashes there resulted in one serious injury, one moderate injury and one minor injury. Washington and 105th did not appear in that top 20.

NE Halsey and 122nd also recorded three pedestrian crashes in those same five years. One person died there. It ranked third. The City considers the number of people involved and the severity of harm as well as how many crashes occurred. The list gives no count for streets outside the top 20. Its pedestrian-only figures cannot be added to the earlier corridor totals.

Portland’s 2020–2024 citywide pedestrian intersection rankings
04The original estimate

How much did engineers allow for the beacons?

The closest public figure we found is an estimate from June 2019. For four planned crossings at 100th and 105th on Stark and Washington, engineers allowed $800,000 in one line for installing pedestrian hybrid beacons, supplemental lighting and the connections between signals. That line included installation. The worksheet gives no separate price for one light or one corner.

The four finished crossings were a larger undertaking. At some corners a ramp or refuge island would displace a storm drain. Crews would have to open the pavement and move the inlet so water could still drain. The estimator also allowed for directing traffic through the work zones.

June 2019 preliminary estimate. Each row includes the one above it. Adding the rows would count the same work more than once.
Scope in the 2019 designEstimated amount
Installed beacons, lighting and connections at four crossings$800,000
All construction for the four crossings, including that equipment$1,740,000
Full four-crossing estimate, including design, property, overhead and contingency$4,572,000

What else matters

The 2019 documents separately estimated $6.532 million for the rest of the corridor. Equipment specifications and design scope can change. The November 2026 funding table gives the current project envelope. We found no current itemized price for the beacon at Washington and 105th.

A question worth asking

How much does today’s design assign to the crossings, how much contingency remains, and what safety benefit would be lost under a lower-cost option? The current engineer’s estimate and an alternatives comparison would let the public test the price.

June 2019 crossing estimate, scope and bid worksheet item 17
October 2019 executive summary, two planning estimates
05Follow the money

Why do two public records differ by $92,580?

Add the five amounts on PBOT’s project page and the total is $11,800,629. The presentation attached to the November 18 Council item shows $11,708,049 for the corridor. Both describe funding. Actual payments to engineers, contractors or property owners would appear in expenditure records.

The largest change is in regional flexible funds. Metro’s 2022 committee papers describe moving about $120,000 from the corridor project into a separate project for travel outreach, combined with similar work on another route. That matches the reduction in the regional line. A July 2025 Metro programming report also shows $5,212,000 in federal funds.

The Council slide separately lists $26,801 in development charges and $619 more in general transportation revenues. The project page divides its general revenues between ADA ramps ($511,629) and quick-build work ($200,000). Read from the project page to the Council slide, the changes add up to −$120,000 + $26,801 + $619 = −$92,580.

Funding sources for the corridor. Project page checked November 20, 2026. Council presentation attached November 18, 2026.
Funding sourcePBOT project pageCouncil slide 5
Regional flexible funds$5,332,000$5,212,000
Fixing Our Streets$5,030,000$5,030,000
Clean Energy Community Benefits Fund$727,000$727,000
General transportation revenues$711,629$712,248
Transportation system development chargesNo separate line$26,801
Total of listed amounts$11,800,629$11,708,049

What else matters

Metro’s July 2025 phase budget totaled $11.442 million. It allocated $8.542 million for construction, $2 million for preliminary engineering, $800,000 for property rights and $100,000 for utilities. Compensation for the current acquisitions remains subject to negotiations.

A question worth asking

When were the two local lines revised, and which funding schedule is current for each phase? A dated project ledger with transfers and expenditures would let residents trace those changes and see what has actually been spent.

PBOT project page and funding list
Funding table in the Council presentation, slide 5
Metro committee packet, March 4 minutes and staff summary for key 22138 (search “$120,000”)
Metro programming report, July 31, 2025, project 71091, p. 113
06At the corner

Why does a crossing signal need an easement?

At SE Washington and 105th, the transportation bureau’s drawing puts a flashing pedestrian beacon on a 15-square-foot permanent easement. Nearby, crews would need temporary access to 147 square feet for sidewalk and ramp work and another 253 for a sidewalk, ramp and driveway. Once construction ends, the beacon still needs a place to stand.

PBOT’s November 18 presentation · funding on slide 5, property rights on slides 7–9
07The decision

What would Council authorize?

PBOT lists 23 owners from whom it needs temporary construction rights and six from whom it needs permanent rights. An owner can fall into both categories. The proposed ordinance would let staff negotiate compensation and, if parties cannot agree, ask a court to resolve it. PBOT could also reduce or drop an acquisition.

The City says it already has funding in project T01035 and describes its confidence in the property estimate as moderate. The December decision concerns access to build the design. The ordinance says construction as planned would be infeasible without those rights.

What else matters

Council advanced the ordinance on November 18. Its action record schedules a second reading for December 2 at 9:30 a.m. Portland time. Residents can follow item 2026-401 on the Council agenda and check the posted testimony options.

Proposed ordinance 2026-401, exhibits and financial impact statement
November 18 Council action
Council agendas, public testimony and meeting access
08What residents said

A safer walk, a slower drive?

PBOT received 223 complete surveys. Of the 209 people who answered the design-support question, 73% supported it. Business owners and employees made up 7% of participants. The outreach documents give readers a sense of what participants valued, but limited evidence about the views of businesses along the route.

Some respondents wanted safer places to walk and bike. Others worried that taking out travel lanes would delay trips or that parked vehicles would block a driver’s view. PBOT found spare road capacity even at peak times. A corridor average can still miss queues at a particular signal or delays to a particular bus.

A question worth asking

After construction, do serious crashes fall, can people cross more easily, and what happens to bus travel times? Comparing those measures with conditions before the work would show how the redesign performs.

Project design and community survey results
PBOT survey findings, January 2026, including question-by-question responses
PBOT open house, crossing distances, speeds and traffic volumes
→The open notebook

Sources and updates

We compared the proposed ordinance with the November 18 Council action, PBOT’s presentation and its project survey. We summed the five funding lines and divided the two largest by that total. The AI-created cover imagines a neighborhood crossing. PBOT’s project documents show the actual design. We used the published crash map window and compared nearby intersections under the same definition. We kept the historic construction estimates, later programmed amounts and current project funding separate.

November 20, 2026 · Added a line-by-line reconciliation of the two public funding totals, Metro’s travel-outreach transfer and an opening guide to Council’s December 2 property-rights decision.

November 20, 2026 · Expanded our original easement story with the intersection crash comparison, the four-crossing estimate and Metro’s earlier phase budget.

Send a correction
Related district coveragePortland City Council District 1Portland City Council District 3Multnomah County District 3