Filed November 20, 2026
Herman Road study favors an all-way stop at Cipole
Washington County Land Use & Transportation. Herman Road users near Tualatin and Sherwood
The County's October 23 project update says its feasibility study found an all-way stop sufficient at Herman and Cipole roads. The wider corridor project between 124th and Cipole includes walking and cycling improvements and has a published $17.3 million estimate through MSTIP 3f. Construction is anticipated from December 2027 to September 2029. The study result is a design-stage finding, not a completed safety outcome.

- Latest scoping updateOct. 23, 2026
- Construction expected to startDecember 2027
- Construction expected to finishSeptember 2029
The county’s Oct. 23 update and project schedule. The construction dates are forecasts for the wider corridor work; the intersection study’s all-way-stop finding is not evidence that the full corridor has been built. Source
- Why it matters here
- An all-way stop would change who yields at Cipole. The $17.3 million estimate also covers the walking and cycling route along Herman Road.
- What you can do
- Read the Oct. 23 design update for the intersection finding, then check the project schedule for when the county expects work to begin. County Herman Road project and October update
Question we’re following Which traffic and safety assumptions support the all-way-stop choice, and how will the final design and cost estimate reflect that decision?